Which statement is true about batch size?
Correct Answer:
C
This statement is true about batch size. Batch size is the amount of work that moves as a unit through a process or system. Large batch sizes increase variability by creating more uncertainty, complexity, dependencies, and unpredictability in the workflow. Large batch sizes also increase waste by causing delays, queues, handoffs, rework, overproduction, and inventory accumulation. Reducing batch size is one of the key ways to optimize value delivery and improve flow efficiency. References: SAFe Lean-Agile Principles, SAFe Principle #5
What is one of the Agile Release Train events?
Correct Answer:
C
A Solution Demo is one of the Agile Release Train (ART) events in the Scaled Agile Framework (SAFe). It is a periodic event that provides an integrated view of the current state of the solution under development. It is typically held at the end of each Program Increment (PI), after the System Demo and before the Inspect and Adapt workshop. The Solution Demo is attended by the Solution Train stakeholders, including Customers, Suppliers, Solution Management, Solution Architect/Engineering, and Release Management. The purpose of the Solution Demo is to evaluate the solution and collect
feedback for improvement. The Solution Demo also provides an opportunity to measure the solution??s fitness for purpose, quality, compliance, and readiness for release
What is found on an ART planning board?
Correct Answer:
A
Features are found on an ART planning board. An ART planning board is a tool that helps teams visualize and manage the work items for an Agile Release Train (ART). An ART is a long-lived team of Agile teams that delivers value in a regular cadence. Features are high-level descriptions of system behaviors that provide business value to a stakeholder. Features are derived from epics and decomposed into user stories or enablers. Features are prioritized by business value using Weighted Shortest Job First (WSJF) and planned for Program Increments (PIs) by the ART teams. References: Organizing Around Value with ARTs, ART Planning Board
Which SAFe Lean-Agile Principle includes the critical part of "delaying decisions to the last responsible moment"?
Correct Answer:
D
The SAFe Lean-Agile Principle that includes the critical part of ??delaying decisions to the last responsible moment?? is ??Assume variability; preserve options??. This principle is based on theconcept of set-based design, which is a way of managing uncertainty and complexity in product development. Set-based design means exploring multiple possible solutions in parallel, eliminating inferior options over time, and converging on the best solution as more information becomes available. Delaying decisions to the last responsible moment means keeping multiple options open until enough data and feedback are gathered to make an informed decision, which reduces risk and waste. References: SAFe Lean-Agile Principles, SAFe Principle #4
A SAFe Portfolio is a collection of what?
Correct Answer:
C
A SAFe portfolio is a collection of development value streams. A development value stream is a long-lived series of steps that an enterprise uses to continuously deliver value to a customer or stakeholder. A development value stream typically consists of one or more ARTs and Solution Trains that build and deliver solutions. A SAFe portfolio aligns and governs one or more development value streams that share a common business mission, vision, strategy, and funding. A SAFe portfolio helps enterprises achieve Lean Portfolio Management, which is one of the core competencies of business agility in
SAFe. References: SAFe Portfolio, Development Value Streams