QUESTION 36

- (Topic 1)
You are coaching Tammy, a project manager in your program, on the benefits of program management. She is stumped as to why you would create a program so you're sharing with her all the difference benefits of a program. Which one of the following is a benefit of creating a program?

  1. A. Programs always cost less than multiple projects in an organization.
  2. B. Project management is centralized to the program manager.
  3. C. Programs provide centralized risk management.
  4. D. Program management makes communication easier among the project managers and project team.

Correct Answer: C

QUESTION 37

- (Topic 3)
Which of the following is used to build consensus through rounds of anonymous surveys?

  1. A. The Pareto chart
  2. B. The Delphi technique
  3. C. The Monte Carlo simulation
  4. D. The Gantt chart

Correct Answer: B

QUESTION 38

- (Topic 2)
Part of program management is to understand how the communication model works in a program. The program manager must be able to effectively communicate with the program team and stakeholders. What component of the communication model is responsible for carrying the message?

  1. A. Medium
  2. B. Sender
  3. C. Decoder
  4. D. Encoder

Correct Answer: A

QUESTION 39

- (Topic 2)
You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?

  1. A. Analogous estimating
  2. B. Organizational process assets
  3. C. Parametric scope definition
  4. D. Template driven

Correct Answer: D

QUESTION 40

- (Topic 3)
You are the program manager for your organization and you are preparing to launch several constituent projects within your program. You need to ensure that each project manager is authorized to utilize the appropriate project and program resources in order to complete the project requirements. What document do you need to create for each
constituent project in your program to ensure that each project manager can use the appropriate resources?

  1. A. Project scope statement
  2. B. Roles and responsibilities chart
  3. C. Project resource requirements document
  4. D. Project charter

Correct Answer: D