QUESTION 21

- (Topic 1)
You are the program manage of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?

  1. A. Project charter for each project
  2. B. Program human resource management plan
  3. C. Project scope statement
  4. D. Program management charter

Correct Answer: A

QUESTION 22

- (Topic 2)
Robert is the program manager for his organization which operates in a matrix structure.
Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another about when the resources will be needed and utilized in the projects. What plan should Robert create along with the project managers to ensure that the resources are scheduled and managed effectively?

  1. A. Resource management plan
  2. B. Program management calendar
  3. C. Schedule management plan
  4. D. Resource calendar

Correct Answer: A

QUESTION 23

- (Topic 1)
You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?

  1. A. It is a roles and responsibilities chart that uses responsible, accountable, consult, and inform responsibilities as the chart legend.
  2. B. It is a roles and responsibilities chart that uses responsible, action, consult, and interest responsibilities as the chart legend.
  3. C. It is a roles and responsibilities chart that uses resource, action, contribute, inform responsibilities as the chart legend.
  4. D. It is a roles and responsibilities chart that uses responsible, accountable, contribute, and inform responsibilities as the chart legend.

Correct Answer: A

QUESTION 24

- (Topic 1)
Which one of the following is NOT a component of the risk monitoring and controlling process?

  1. A. Executing risk response plans
  2. B. Completing quantitative risk analysis
  3. C. Tracking identified risks
  4. D. Determining if new risks have developed

Correct Answer: B

QUESTION 25

- (Topic 3)
____ is the degree to which a set of inherent characteristics fulfills requirements.

  1. A. Scope
  2. B. Project phase
  3. C. Regulation
  4. D. Quality

Correct Answer: D