QUESTION 16

- (Topic 4)
Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

  1. A. Program transition agreement
  2. B. Program scope statement
  3. C. Operational transfer alliance plan
  4. D. Program milestone list

Correct Answer: A

QUESTION 17

- (Topic 1)
A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent $620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario?

  1. A. Schedule, because the program's planned value is only $700,000.
  2. B. Cost, because the program has a cost variance of -7,500
  3. C. Schedule, because the program has a schedule performance index of .88.
  4. D. Cost, because the program has an estimate to complete of $1,151,429.

Correct Answer: C

QUESTION 18

- (Topic 3)
Don is the project manager of the NQP Project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. What document should Don reference for information on the activities and the regulations?

  1. A. Risk management plan
  2. B. Risk register
  3. C. Activity list
  4. D. Activity list and attributes

Correct Answer: D

QUESTION 19

- (Topic 2)
You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?

  1. A. The contract type requires the vendor to provide a fee for the time invested and the materials used.
  2. B. The contract type allows the vendor to change the price of the work he's completed.
  3. C. The contract type allows is the most dangerous for the buyer.
  4. D. The contract type requires the vendor to provide a fixed price for the work.

Correct Answer: C

QUESTION 20

- (Topic 3)
Who owns the program?

  1. A. Program manager
  2. B. Project manager
  3. C. Program director
  4. D. Program sponsor

Correct Answer: C