QUESTION 11

- (Topic 3)
You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?

  1. A. Approved change requests
  2. B. Performance reports
  3. C. Stakeholder analysis charts
  4. D. Communications management plan

Correct Answer: D

QUESTION 12

- (Topic 1)
Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

  1. A. The schedule is performing worse because the SPI is .90
  2. B. The cost is performing worse because the EAC is $1,611,111.
  3. C. The schedule is performing worse because the SV is -$27,500.
  4. D. The cost is performing worse because the CPI is .96.

Correct Answer: A

QUESTION 13

- (Topic 3)
You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager, create at this time?

  1. A. Operational transfer plan
  2. B. Program closure reports
  3. C. Life cycle costing estimates
  4. D. Lessons learned documentation

Correct Answer: B

QUESTION 14

- (Topic 2)
You are hosting a meeting with all of the vendors that have received a copy of your statement of work. In this meeting, you'll be discussing the statement of work, clarifying the details, and answering any questions nos the vendors may have about the project. What is this meeting called?

  1. A. Sales meeting
  2. B. Select sellers process
  3. C. Bidder conference
  4. D. Negotiations

Correct Answer: C

QUESTION 15

- (Topic 3)
You are the program manager for a new software development program. One of the developers has been adding extra fields for information in the software that was not part of the original program scope. While the fields are a good idea, the customer did not ask for the information and some time has been wasted on this work that was not in the program scope. This is an example of which one of the following terms?

  1. A. Preventive action
  2. B. Corrective action
  3. C. Gold plating
  4. D. Program scope change

Correct Answer: D