QUESTION 6

- (Topic 1)
You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that can happen in any order?

  1. A. Finish on constraints
  2. B. Discretionary dependencies
  3. C. Mandatory dependencies
  4. D. Benefits management dependencies

Correct Answer: B

QUESTION 7

- (Topic 2)
You are the program manager for your organization and are working with Tracy, one of the project managers in your program. Tracy is having some trouble understanding the concept of the critical path in her project's network diagram. Which one of the following is the best definition of the critical path?

  1. A. It is the path that carries the most risk of project failure.
  2. B. It is the path that reveals the earliest date the project can finish.
  3. C. It is the path with the most important activities in the project.
  4. D. It is the duration of all the project activities if the labor is summed.

Correct Answer: B

QUESTION 8

- (Topic 1)
Joan is the program manager for her organization. Management has asked her to create a centralized reporting system to capture information on program work, risks, changes, benefits management, and other aspects of the program. What solution can Joan implement to capture, communicate, and record the information management wants?

  1. A. Program management information system
  2. B. Program management integrated change control
  3. C. Change control systems
  4. D. Program management plan execution

Correct Answer: A

QUESTION 9

- (Topic 1)
You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must
review the work your project team has completed and determine if the project should be allowed to continue. What name describes this type of end-of-phase review management is completing on your project?

  1. A. Quality control
  2. B. Kill point
  3. C. Phase review
  4. D. Audit

Correct Answer: B

QUESTION 10

- (Topic 2)
You are the program manager for your organization and are planning the composition of the project team. In your organization resources are used from throughout the company and may serve on more than one project. While you, the program manager, will have most of the authority on the program you want the project managers to have authority over the project decisions. What type of an organizational structure does your organization have?

  1. A. Strong Matrix
  2. B. Functional
  3. C. Weak Matrix
  4. D. Projectized

Correct Answer: A