QUESTION 91

- (Topic 2)
You are the program manager for your organization. One of the projects within your program is to install 15,000 light fixtures throughout your organization's corporate campus. The new fixtures will save on electrical costs. Which one of the following choices is an ideal approach to quality assurance and the installation of the light fixtures for this project team?

  1. A. The cost and time of each installation should go down because of the learning curve.
  2. B. The project manager should work with the project team to understand how each fixture is to be installed.
  3. C. The project team members should develop their own system for installation of the fixtures.
  4. D. Use a checklist for the installation because it is repeatable work.

Correct Answer: D

QUESTION 92

- (Topic 4)
What is another term that can be assigned to the pre-program analysis and research to determine if a program should be initiated?

  1. A. Program charter creation
  2. B. Feasibility study creation
  3. C. Business case creation
  4. D. Program scope statement definition

Correct Answer: B

QUESTION 93

- (Topic 3)
June is the program manager for her organization. Management has asked June to create a visual mapping of the program scope so that all of the key stakeholders can see all of the elements of the program scope. June needs to create what kind of document to show all of the program deliverables based on the program scope?

  1. A. Program network diagram
  2. B. Program benefits mapping chart
  3. C. Program budget
  4. D. Program work breakdown structure

Correct Answer: D

QUESTION 94

- (Topic 3)
Which of the following documents is described in the statement below?
"It is a type of procurement document used to request proposals from prospective sellers of products or services."

  1. A. Request for information
  2. B. Request for quote
  3. C. Request for proposal
  4. D. Request for bid

Correct Answer: C

QUESTION 95

- (Topic 2)
You need to create a document that will define the costs, resources, and characteristics of each deliverable the program will create. What document should you create?

  1. A. Program work breakdown structure
  2. B. Program work breakdown structure dictionary
  3. C. Program charter
  4. D. Program scope statement

Correct Answer: B