QUESTION 56

- (Topic 1)
You are the program manager for your organization and are working on gathering the requirements for a new solution and mission statement. There are several instances in the stakeholder pool where the stakeholders and their manager are being queried on possible requirements. You worry that the subordinates may have requirements, ideas, and suggestions to offer but they may be not submitting their thoughts because they do not want to contradict their managers. You believe you need a method to gather all requirements without the stakeholders having any fear of retribution. Which one of the following allows you to anonymously gather iterations requirements and still allow for all stakeholders to review what has been submitted in an attempt to find consensus?

  1. A. Delphi Technique
  2. B. Focus groups
  3. C. Web surveys
  4. D. Workshops

Correct Answer: A

QUESTION 57

- (Topic 1)
Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines
the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?

  1. A. Quality Management System
  2. B. Change Control System
  3. C. Project Management Information System
  4. D. Integrated Change Control System

Correct Answer: C

QUESTION 58

- (Topic 2)
You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work. The outsourcing of the dangerous work to a specialist is what type of risk response?

  1. A. Avoidance
  2. B. Mitigation
  3. C. Transference
  4. D. Enhancing

Correct Answer: C

QUESTION 59

- (Topic 2)
You are the program manager for your organization and are working with your team to create the program scope management plan. This plan defines several things in your program except for which one of the following?

  1. A. How quality control will be included in the scope
  2. B. How changes may be allowed to enter the program scope
  3. C. How the program scope will be created for your program
  4. D. How the program scope will be controlled

Correct Answer: A

QUESTION 60

- (Topic 2)
Gina is the program manager for her organization and is reviewing the results of quality control. She would like to create a chart that shows the categories of defects within the program so that she and the program team can address the largest categories in descending order. Which one of the following is the best chart for Gina in this situation?

  1. A. Cause and effect chart
  2. B. Pareto chart
  3. C. Control chart
  4. D. Ishikawa chart

Correct Answer: B