During the execution of a construction project, one of the neighboring businesses is complaining that the current building height does not agree with the initial project plans. What should the project manager do first?
Correct Answer:
D
A project manager starts to receive emails from different stakeholders requesting information about the project status. What should the project manager do to avoid this in the future?
Correct Answer:
B
An organization is initiating a project that will be using new technology. The complexity of the project requires excellent technical skills. After reviewing the proposed project management plan, the project sponsor asks for options to reduce the labor cost without introducing risk to the project delivery.
What should the project manager do first?
Correct Answer:
C
A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?
Correct Answer:
B
An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?
Correct Answer:
A