A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is identified regarding an indirect tax regulation that is being changed by the government in the next 6 months.
This risk will have a significant impact on the project outcomes.
What should the project manager do next?
Correct Answer:
C
An agile team has sized all of the features for the release. Using the table above, how many sprints will it take to complete this release if the team is expecting to have a velocity of 10 story points per sprint?
Correct Answer:
B
A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?
Correct Answer:
D
Anew project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25%. The project manager updated the risk register and kept the project running as normal. The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.
What should the project manager have done to avoid this?
Correct Answer:
A
A global program is being kicked off, and various distributed teams are involved in delivering the initiative.
Besides planning and executing the scope for the initiative, team interactions must be considered.
How should the project teams interact in their meetings?
Correct Answer:
B