Free PMI-RMP Exam Braindumps

Pass your PMI Risk Management Professional exam with these free Questions and Answers

Page 9 of 23
QUESTION 36

You are the project manager for BlueWell Inc. You are reviewing the risk register for your project. The risk register provides much information to you, the project manager and to the project team during the risk response planning. All of the following are included in the risk register except for which item?

  1. A. Network diagram analysis of critical path activities
  2. B. Symptoms and warning signs of risks
  3. C. List of potential risk responses
  4. D. Trends in qualitative risk analysis results

Correct Answer: A

QUESTION 37

You are the project manager of the CUL project in your organization. You and the project team are assessing the risk events and creating a probability and impact matrix for the identified risks. Which one of the following statements best describes the requirements for the data type used in qualitative risk analysis?

  1. A. A qualitative risk analysis requires fast and simple data to complete the analysis.
  2. B. A qualitative risk analysis requires accurate and unbiased data if it is to be credible.
  3. C. A qualitative risk analysis encourages biased data to reveal risk tolerances.
  4. D. A qualitative risk analysis required unbiased stakeholders with biased risk tolerances.

Correct Answer: B

QUESTION 38

Which of the following components ensures that risks are examined for all new proposed change requests in the change control system?

  1. A. Risk monitoring and control
  2. B. Scope change control
  3. C. Integrated change control
  4. D. Configuration management

Correct Answer: C

QUESTION 39

Mike is the project manager of the NNP Project for his organization. He is working with his project team to plan the risk responses for the NNP Project. Mike would like the project team to work together on establishing risk thresholds in the project. What is the purpose of a risk threshold?

  1. A. It helps to identify those risks for which specific responses are needed.
  2. B. It is a limit of the funds that can be assigned to risk events.
  3. C. It is a warning sign that a risk event is going to happen.
  4. D. It is a study of the organization's risk tolerance.

Correct Answer: A

QUESTION 40

John works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk?

  1. A. Activity duration estimates
  2. B. Schedule management plan
  3. C. Risk management plan
  4. D. Activity cost estimates

Correct Answer: A

Page 9 of 23

Post your Comments and Discuss PMI PMI-RMP exam with other Community members: