Free PMI-RMP Exam Braindumps

Pass your PMI Risk Management Professional exam with these free Questions and Answers

Page 6 of 23
QUESTION 21

You work as the project manager for Bluewell Inc. Your project has several risks that will affect several stakeholder requirements. Which project management plan will define who will be available to share information on the project risks?

  1. A. Risk Management Plan
  2. B. Stakeholder management strategy
  3. C. Resource Management Plan
  4. D. Communications Management Plan

Correct Answer: D

QUESTION 22

Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen.
If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?

  1. A. $35,000
  2. B. $41,700
  3. C. $14,000
  4. D. $6,700

Correct Answer: D

QUESTION 23

John works as a project manager for ABD project. He and his team, are working on the following activities:
Relative ranking or priority list of project risks Watchlists of low priority risk
Trends in Qualitative Risk Analysis results
On which of the following processes is John working on?

  1. A. Perform Qualitative Risk Analysis
  2. B. Plan Risk Management
  3. C. Plan Risk Responses
  4. D. Perform Quantitative Risk Analysis

Correct Answer: A

QUESTION 24

You are the project manager for TTP project. You are in the Identify Risks process. You
have to create the risk register. Which of the following are included in the risk register? Each correct answer represents a complete solution. Choose two.

  1. A. List of mitigation techniques
  2. B. List of key stakeholders
  3. C. List of identified risks
  4. D. List of potential responses

Correct Answer: CD

QUESTION 25

Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?

  1. A. Project risk management is scheduled for every month in the 18-month project.
  2. B. Project risk management has been concluded with the project planning.
  3. C. At every status meeting the project team project risk management is an agenda item.
  4. D. Project risk management happens at every milestone.

Correct Answer: C

Page 6 of 23

Post your Comments and Discuss PMI PMI-RMP exam with other Community members: