QUESTION 11

You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than 0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?

  1. A. 1.06
  2. B. 0.92
  3. C. -$30,647
  4. D. 0.93

Correct Answer: D

QUESTION 12

You are working with the project stakeholders to analyze and prioritize their requirements for the project. One of the project requirements is to achieve a high-level of customer satisfaction for the project deliverable. What is the danger in this project requirement?

  1. A. Achieving customer satisfaction is an assumption and should be documented in the project scope.
  2. B. Achieving customer satisfaction is a subjective requirement and entails a high level of risk of being successfully accomplished.
  3. C. Achieving customer satisfaction is a risk as the project manager cannot control how satisfied the customer will be with the project deliverables.
  4. D. Achieving customer satisfaction should always map to the quality requirements for the project.

Correct Answer: B

QUESTION 13

You are the project manager for Genpact Inc. You have established quarterly risk management meetings. Which of the following is not a component of a risk management meeting?

  1. A. Assessing the overall status of risks in the project
  2. B. Review of risk responses
  3. C. Assessment or risk
  4. D. The availability of the individual

Correct Answer: D

QUESTION 14

Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?

  1. A. Risk register
  2. B. Risk register updates
  3. C. Change requests
  4. D. Project document updates

Correct Answer: A

QUESTION 15

Which risk response is acceptable for both positive and negative risk events?

  1. A. Transferring
  2. B. Acceptance
  3. C. Sharing
  4. D. Enhancing

Correct Answer: B