Free PMI-RMP Exam Braindumps

Pass your PMI Risk Management Professional exam with these free Questions and Answers

Page 12 of 23
QUESTION 51

Consider a project with a budget at completion of $1,345,000 and it is supposed to be completed by today, but it is only 80 percent complete. This project has spent $1,250,000 to reach this point of completion. What is the schedule variance for this project?

  1. A. -$217,500
  2. B. 20 percent
  3. C. -$174,000
  4. D. -$269,000

Correct Answer: D

QUESTION 52

The risk transference is referred to the transfer of risks to a third party, usually for a fee, it creates a contractual-relationship for the third party to manage the risk on behalf of the performing organization. Which one of the following is NOT an example of the transference risk response?

  1. A. Use of insurance
  2. B. Warranties
  3. C. Life cycle costing
  4. D. Performance bonds

Correct Answer: C

QUESTION 53

The Project Risk Management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Choose all that apply.

  1. A. Quantitative Risk Analysis
  2. B. Risk Monitoring and Control
  3. C. Potential Risk Monitoring
  4. D. Risk Management Planning

Correct Answer: ABD

QUESTION 54

Harry works as a project manager for BlueWell Inc. He is determining how to conduct the risk management activities for a project. According to the PMBOK, there are six inputs to the plan risk management process. Which one of the following is NOT an input to this process?

  1. A. Project scope statement
  2. B. Risk management plan
  3. C. Schedule management plan
  4. D. Cost management plan

Correct Answer: B

QUESTION 55

David is the project manager of the NKL Project for his organization. He has been asked to create a proposal for a construction project for a client. David realizes that there are several requirements within the SOW and RFP provided by the client that would eliminate his company from bidding on the construction project. David proposed to management that his organization create a partnership with a competitor so that together they could bid on the construction project and qualify for the customer's requirements. What risk response is David proposing to management?

  1. A. Exploiting
  2. B. Teaming agreement
  3. C. Transference
  4. D. Sharing

Correct Answer: D

Page 12 of 23

Post your Comments and Discuss PMI PMI-RMP exam with other Community members: