QUESTION 46

Lamont is the project manager of a project that has recently finished the final project deliverables. The project customer has signed off on the project deliverable and Lamont has a few administrative closure activities to complete. In the project, there were several large risks that could have wrecked the project but Lamont and his project team found some creative methods to resolve the risks without affecting the project costs or project end date. What should Lamont do with the risk responses he identified during the project's monitoring and controlling process?

  1. A. Include the risk response in the project risk management plan.
  2. B. Include the responses in the project management plan.
  3. C. Nothin
  4. D. The risk responses are included in the project's risk register already.
  5. E. Include the risk responses in the organization's lessons learned database.

Correct Answer: D

QUESTION 47

You are the project manager of the GHY project for your organization. You are about to start the qualitative risk analysis process for the project and you need to determine the roles and responsibilities for conducting risk management. Where can you find this information?

  1. A. Enterprise environmental factors
  2. B. Risk register
  3. C. Risk management plan
  4. D. Staffing management plan

Correct Answer: C

QUESTION 48

Fred is the project manager of the CPS project. He is working with his project team to prioritize the identified risks within the CPS project. He and the team are prioritizing risks for further analysis or action by assessing and combining the risks probability of occurrence and impact. What process is Fred completing?

  1. A. Risk identification
  2. B. Perform qualitative analysis
  3. C. Perform quantitative analysis
  4. D. Risk Breakdown Structure creation

Correct Answer: B

QUESTION 49

Harold is the project manager of a large project in his organization. He has been actively communicating and working with the project stakeholders. One of the outputs of the manage stakeholder expectations process can actually create new risk events for Harold's project. Which output of the manage stakeholder expectations process can create risks?

  1. A. Project document updates
  2. B. Change requests
  3. C. Organizational process assets updates
  4. D. Project management plan updates

Correct Answer: B

QUESTION 50

Don has hired Jerry, a contractor, to complete a portion of his project work. The contract used was a cost-plus contract. If Don were to perform a risk audit, who would carry the risk in this scenario?

  1. A. Don would because he is the project manager.
  2. B. Jerry would because of the contract type.
  3. C. Don would because of the contract type.
  4. D. Jerry would because he is the hired contractor.

Correct Answer: C

Page 11 of 23