Holly is the project manager of the NSS Project for her company. She is discussing some of the project risks and the issues that have happened in the project. Holly has faxed the status report to her project client for their review. Based on the standard communication model, which component in this scenario is the decoder?
Correct Answer:
D
John is the project manager of the NHQ Project for his company. His project has 75 stakeholders, some of which are external to the organization. John needs to make certain that he communicates about risk in the most appropriate method for the external stakeholders. Which project management plan will be the best guide for John to communicate to the external stakeholders?
Correct Answer:
C
You are the project manager of the NHH Project for your company and you have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Now, you would like to assign risk owners to the events. Which risk events should have risk response owners?
Correct Answer:
B
Your organization has a project that is expected to last 20 months but the customer would really like the project completed in 18 months. You have worked on similar projects in the past and believe that you could fast track the project and reach the 18 month deadline. What increases when you fast track a project?
Correct Answer:
D
Which of the following diagrams displays sensitivity analysis data?
Correct Answer:
C