QUESTION 41

Holly is the project manager of the NSS Project for her company. She is discussing some of the project risks and the issues that have happened in the project. Holly has faxed the status report to her project client for their review. Based on the standard communication model, which component in this scenario is the decoder?

  1. A. Project customer
  2. B. Telephone wire
  3. C. Holly
  4. D. Project customer's fax machine

Correct Answer: D

QUESTION 42

John is the project manager of the NHQ Project for his company. His project has 75 stakeholders, some of which are external to the organization. John needs to make certain that he communicates about risk in the most appropriate method for the external stakeholders. Which project management plan will be the best guide for John to communicate to the external stakeholders?

  1. A. Risk Response Plan
  2. B. Risk Management Plan
  3. C. Communications Management Plan
  4. D. Project Management Plan

Correct Answer: C

QUESTION 43

You are the project manager of the NHH Project for your company and you have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Now, you would like to assign risk owners to the events. Which risk events should have risk response owners?

  1. A. Only the risks with a high risk rating
  2. B. Each agreed-to and funded risk response should have a risk response owner
  3. C. Each risk that has a risk response should have a risk response owner
  4. D. Only the risk events that are considered a negative risk event with a high risk rating

Correct Answer: B

QUESTION 44

Your organization has a project that is expected to last 20 months but the customer would really like the project completed in 18 months. You have worked on similar projects in the past and believe that you could fast track the project and reach the 18 month deadline. What increases when you fast track a project?

  1. A. Resources
  2. B. Costs
  3. C. Communication
  4. D. Risks

Correct Answer: D

QUESTION 45

Which of the following diagrams displays sensitivity analysis data?

  1. A. Fishbone
  2. B. Influence
  3. C. Tornado
  4. D. Cause and effect

Correct Answer: C