QUESTION 11

The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?

  1. A. Conduct user acceptance testing.
  2. B. Conduct performance testing.
  3. C. Evaluate the solution with the sponsor(s).
  4. D. Evaluate the solution against the project charter.

Correct Answer: A

QUESTION 12

A company's management team has decided to deploy a new product. However, there is concern that users may not accept a new product that forces them to change existing practices.
The business analyst should:

  1. A. delay the application's deployment until the conflicts have been resolved.
  2. B. voice user concerns to management and recommend that the project be closed.
  3. C. adhere to the project plan to achieve project objectives.
  4. D. clearly communicate project objectives and attempt to defuse tensions.

Correct Answer: D

QUESTION 13

A project was in the design phase when the team received news of a new regulatory mandate that affects the project. The requirements have already been approved and baselined. If the new requirements are not included, the company will be out of compliance and may face monetary penalties.
What should the business analyst do next?

  1. A. Update the requirements
  2. B. Obtain approval from the project manager
  3. C. Follow the change control process
  4. D. Define the project scope

Correct Answer: C

QUESTION 14

The business analyst is in the process of implementing a solution for a customer. The team is having difficulty confirming if certain requirements have been met. What could have caused this issue?

  1. A. The test engineer has not properly communicated requirements to the team.
  2. B. Acceptance criteria for the requirements were not measurable.
  3. C. Requirements were not adequately reviewed with the project sponsor.
  4. D. Not all stakeholders were involved during requirements elicitation

Correct Answer: B

QUESTION 15

A business analyst is working on a system enhancement project and has completed the requirements according to the requirements management plan. The business analyst is now ready to request approval from the stakeholders.
How should the business analyst obtain approval?

  1. A. Provide a defect tracking log for review.
  2. B. Conduct a formal or informal review of the requirements.
  3. C. Send an email requesting approval of requirements.
  4. D. Create and maintain an audit history log of changes to requirements.

Correct Answer: B