What should an agile practitioner do to ensure that the end product meets business requirements?
Correct Answer:
D
During iteration planning, it was determined that an epic should be decomposed. What was the determining factor?
Correct Answer:
A
A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?
Correct Answer:
C
Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so tar on the project How should the agile practitioner explain to server management the benefits of this approach?
Correct Answer:
D
An agile practitioner becomes a Scrum Master on an established Scrum team. After introductions, what should the agile practitioner do?
Correct Answer:
D