QUESTION 31

A product owner for two highly visible projects spends a great deal of time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because
both project teams request clarification on the requirements and the overall priorities. What should the agile project manager do?

  1. A. Provide both project teams with the highest priority needs.
  2. B. Request the project teams' questions in writing prior to the next meeting.
  3. C. Facilitate a meeting with each team and the product owner to find a solution.
  4. D. Provide both teams with each project's documentation.

Correct Answer: C

QUESTION 32

Midway through a sprint. a scrum team member advises the team of a new requirement Dial may change the initial scope What should the team do?

  1. A. Work on requirements that (he product owner may have overlooked
  2. B. Record the scope creep m the change management tog
  3. C. Add the new requirement to the product backlog
  4. D. Ask the scrum master to secure additional time and resources

Correct Answer: D

QUESTION 33

The product owner wants to build security firewalls into the product. How can the team members support this?

  1. A. Add new security features to the backlog and prioritize.
  2. B. Execute a spike to research security features for the project.
  3. C. Ask questions to determine where and how the product owner wants to use the product.
  4. D. Ask questions to determine if the product owner can define the desired level of security.

Correct Answer: C

QUESTION 34

During its first sprint a new scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories. What should the team do?

  1. A. Cross-tram some members in the automation framework to broaden their capacity with that skill
  2. B. Ask the product owner to add team members to boost this particular skill set
  3. C. Send a member to automation framework training when funds are available
  4. D. Avoid using test automation by swarming on the testing tasks and using manual testing

Correct Answer: B

QUESTION 35

A client slates that a product is not being built as requested. How should the agile team address this?

  1. A. Conduct an internal review to validate functionality before shipping
  2. B. Audit the quality control process to ensure that the product adheres to requirements.
  3. C. Lengthen iterations to ensure there is sufficient time to build functionality
  4. D. Hold product review sessions with the client to obtain product acceptance.

Correct Answer: B