QUESTION 26

Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?
PMI-ACP dumps exhibit

  1. A. The iteration is in jeopardy.
  2. B. The team has removed scope.
  3. C. The iteration is ahead of schedule.
  4. D. The team's velocity is constant.

Correct Answer: A

QUESTION 27

During an iteration, an agile team discovers infrastructure requirements that were not initially considered. What should the team do to effectively manage this?

  1. A. Rework the iteration scope to accommodate these requirements.
  2. B. Add these requirements into the product backlog for future consideration.
  3. C. Raise the discovery of these requirements as an issue, and escalate to management.
  4. D. Immediately start working on these requirements.

Correct Answer: B

QUESTION 28

A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.
What should the scrum master do?

  1. A. Tell the technical lead to do the testing.
  2. B. Facilitate an open and focused team discussion that reinforces team agreements.
  3. C. Ask the team manager to advise the technical lead that all tasks are important.
  4. D. Encourage the team to take ownership of the delivery.

Correct Answer: B

QUESTION 29

A project Worn meets to estimate user stones for a sprint. While an important non-functional requirement must be delivered in the sprint the estimate exceeds sprint capacity.
What should the team do?

  1. A. Estimate only functional requirements that will impact product quality
  2. B. Add learn resources
  3. C. Refer the issue to the product owner
  4. D. Break non-functional requirements into those that can be delivered in the given sprint

Correct Answer: C

QUESTION 30

An agile coach is assigned to help a project learn that was recently co-located dose to a very popular business Many team members visit this business during working hours which affects team performance What should the agile coach do to mitigate this issue?

  1. A. Speak with the functional managers and come to an agreement that will resolve the issue
  2. B. Explain to functional managers that too much control will inversly impact team morale
  3. C. Meet with the team to discuss the issue and identify specific actions to reduce or eliminate the issue
  4. D. inform the team there will be penalties to anyone who visits that business during working hours

Correct Answer: C