QUESTION 21

An agile team member identifies a potential problem within the project team How should the team's coach react?

  1. A. Document the problem escalate to the project manager, and develop a solution for the team
  2. B. Add the problem to the backlog and assign resolution to a future iteration
  3. C. Instruct the team to try to solve the problem within the team
  4. D. Perform root cause analysis and report the problem to the product owner

Correct Answer: C

QUESTION 22

At the retrospective, the burndown chart shows that the project is slightly behind schedule. The project team identifies an inexperienced software engineer as the source of reduced velocity-How should the project team address this issue?

  1. A. Suggest pair programming during the retrospective.
  2. B. Ask the product owner to re-prioritize the user stories at the next retrospective.
  3. C. Re-estimate the story points with team members at the next iteration planning meeting.
  4. D. Assign less complex user stories to the inexperienced software engineer at the next iteration planning meeting.

Correct Answer: A

QUESTION 23

A team is transitioning from a predictive approach to an agile approach. Historically, the team has delivered work products that did not meet customer expectations. What agile practice can help the team to alleviate this?

  1. A. Test-driven development (TDD)
  2. B. Clear definition of done and regular demos
  3. C. Collaborative team planning games
  4. D. Consistent team velocity

Correct Answer: B

QUESTION 24

A scrum team has conducted regular retrospectives to discuss immediate concerns and the implementation of improvement actions. Despite this, after a few iterations, the same concerns resurface.
What should the team have done to improve retrospective outcomes?

  1. A. Invited subject matter experts (SMEs)
  2. B. Conducted problem detection to determine root causes
  3. C. Measured and reported the outcome of improvement actions to the team
  4. D. Kept track of all current issues in a log, and then reviewed their progress at the end of every iteration

Correct Answer: A

QUESTION 25

Based on me burndown chart, what is the iteration's status?
PMI-ACP dumps exhibit

  1. A. It trended ahead of schedule and completed everything on time
  2. B. It took more time than expected and had to be lengthened
  3. C. It trended behind schedule and did not complete everything on time
  4. D. It took less time than expected and had to be shortened

Correct Answer: C