An agile team member identifies a potential problem within the project team How should the team's coach react?
Correct Answer:
C
At the retrospective, the burndown chart shows that the project is slightly behind schedule. The project team identifies an inexperienced software engineer as the source of reduced velocity-How should the project team address this issue?
Correct Answer:
A
A team is transitioning from a predictive approach to an agile approach. Historically, the team has delivered work products that did not meet customer expectations. What agile practice can help the team to alleviate this?
Correct Answer:
B
A scrum team has conducted regular retrospectives to discuss immediate concerns and the implementation of improvement actions. Despite this, after a few iterations, the same concerns resurface.
What should the team have done to improve retrospective outcomes?
Correct Answer:
A
Based on me burndown chart, what is the iteration's status?
Correct Answer:
C