QUESTION 16

During project inception an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision The stakeholder asks for detailed requirements design, and delivery plans What should the agile practitioner do?

  1. A. Provide all information requested by the stakeholder
  2. B. Set expectations regarding the appropriate level of details requested during this stage
  3. C. inform the stakeholder mat no detailed documents are provided using agile practices
  4. D. Ask the team to supply the information 10 the stakeholder

Correct Answer: B

QUESTION 17

Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release. What should the team do?

  1. A. Conduct frequent demos and obtain feedback from users throughout the development of the next release.
  2. B. Inform senior management that since the product was successfully released, the project is considered delivered and should be closed.
  3. C. Request additional budget to implement a Scrum of Scrums approach to scale the teams and add capacity.
  4. D. Implement a better definition of done to ensure that continuous integration processes are managed effectively.

Correct Answer: A

QUESTION 18

A seven-member agile team's composition vanes considerably in age, gender culture, personality type and professional background. When planning a team-building event, what type of interpersonal skills should the project leader use?

  1. A. Networking
  2. B. Social awareness
  3. C. Communication
  4. D. Leadership

Correct Answer: D

QUESTION 19

An agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released What should the agile team do?

  1. A. Demand frequent product reviews by the product owner
  2. B. Continuously work with the product owner to do backlog refinement and product reviews
  3. C. Have the product owner provide detailed requirement specifications to ensure the proper features are delivered
  4. D. During the planning session ensure the team is committed to deliver within the specifications

Correct Answer: B

QUESTION 20

A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time. What should the product owner do?

  1. A. Schedule regular meetings with the scrum team to write, groom, and size user stories.
  2. B. Focus on stories based on the highest number of story points to first address those items with the highest value.
  3. C. Seek regular input from project stakeholders, and reflect this input in the backlog's priorities.
  4. D. Schedule in-person, monthly meetings with key stakeholders to review the project's progress.

Correct Answer: C