QUESTION 1

A newly formed development learn experienced difficulty with accurately estimating product backlog items As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations
What should the team do to improve the accuracy of their estimates?

  1. A. Decrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog tn a single sprint
  2. B. Discuss estimating techniques in the daily scrum meeting
  3. C. Increase the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint
  4. D. Begin tracking estimated effort metrics as an input to performance evaluation.

Correct Answer: B

QUESTION 2

On an agile project some of the development team is struggling to understand how the tasks and use stones fit into the overall product. How should this be addressed?

  1. A. Review the iteration goals and have the team each describe the work to create shared understanding
  2. B. Create a story map for the minimal viable product (MVP) functionality
  3. C. Capture this as a task in the retrospective and ensure there is more detail provided at the next planning session.
  4. D. Have the product owner explain the product vision and review the release plan with the team

Correct Answer: B

QUESTION 3

During a team meeting, members who are subject matter experts (SMEs) mention that they are continuously working on repetitive tasks, which has lowered motivation. What should the agile practitioner do?

  1. A. Organize a team-building activity to improve team morale.
  2. B. Have team members work in pairs to learn from each other and develop new skills.
  3. C. Ask team members to perform a value stream analysis of their activities.
  4. D. Add more resources to the team to help with the tasks.

Correct Answer: B

QUESTION 4

During a retrospective the agile practitioner discovers that a team member's process improvement idea has worsened the outcome What should the agile practitioner do?

  1. A. Commend the team on
  2. B. trying the idea then encourage discussion regarding alternatives
  3. C. Ask a manager to direct the team on fixing the process
  4. D. Encourage the team to continue executing the idea to see if it improves
  5. E. Privately speak with the learn member to convey that their idea worsened the outcome

Correct Answer: D

QUESTION 5

The executive leadership wants to understand ways to better deliver on time and on budget. What can the project team do to assist in achieving the organizational goal?

  1. A. Maintain and review a lessons learned repository to improve delivery of future projects.
  2. B. Ask each team member to post corrective action to the backlog.
  3. C. Engage the project management office (PMO) to take responsibility identifying lessons learned on projects.
  4. D. Perform a root cause analysis to identify alternative approaches for performing the next project.

Correct Answer: A