QUESTION 11

- (Exam Topic 3)
You create a solution within a Microsoft Power Platform environment. The environment includes all connections required for the solution.
You need to create a connection reference for the flows.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the order.
PL-500 dumps exhibit
Solution:
PL-500 dumps exhibit

Does this meet the goal?

  1. A. Yes
  2. B. No

Correct Answer: A

QUESTION 12

- (Exam Topic 1)
You need to ensure that the solution uses the correct accounts payable mailbox. Which three actions should you perform? Each correct answer part of the solution, NOTE: Each correct selection is worth one point.

  1. A. Set the current value for the accounts payable mailbox in the environment.
  2. B. Set the default value for the accounts payable mailbox in the environment.
  3. C. Turn off and then turn on the cloud flows.
  4. D. Use separate environment variables for the cloud flow and the canvas app.
  5. E. Use one environment variable for both the cloud flows and the canvas app.

Correct Answer: ACD

QUESTION 13

- (Exam Topic 2)
You need to package the automations. What should you do?

  1. A. Show dependencies within the solution.
  2. B. Remove unmanaged layers.
  3. C. Add required components to each item within the solution.
  4. D. Add existing components to the solution.

Correct Answer: B

QUESTION 14

- (Exam Topic 3)
You are creating a custom selector for a Microsoft Excel workbook by using a Power Automate desktop flow.
PL-500 dumps exhibit
PL-500 dumps exhibit
Solution:
PL-500 dumps exhibit

Does this meet the goal?

  1. A. Yes
  2. B. No

Correct Answer: A

QUESTION 15

- (Exam Topic 3)
You create several desktop flows. Each flow will run on a single user's device. You need to determine how Power Automate will orchestrate the flows.
Which three rules will Power Automate apply? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.

  1. A. All the flows are run simultaneously.
  2. B. The next flow will run when each run completes based on the priority and the time requested.
  3. C. The first flow runs on the target device based on the priority and the time requested.
  4. D. The first flow runs on the target device based on Next to run status and time requested.
  5. E. The first and last flows run based on the priority and the time requested.
  6. F. The remaining flows are queued.

Correct Answer: AEF