QUESTION 6

Your customer plans to use HPE Primera to boot HPE Synergy compute nodes. They currently have two HPE Virtual Connect SE 100Gb F32 Module for Synergy modules installed in the frame. The customer wants to use FC as a storage access protocol
What must be done to complete this task?

  1. A. Enable FC primary and secondary boot on the modules through the HPE OneView interface
  2. B. FC connectivity on the modules should be enabled through the service console by disabling FCoE.
  3. C. Add FC upgrade licenses in HPE OneView that will enable FC connectivity for the modules
  4. D. Enter both modules into a maintenance mode, then enable FC connectivity through CLI

Correct Answer: B

QUESTION 7

Your customer plans to deploy HPE Superdome Flex and configure two nPars, each based on two chassis Which components must be included in the proposal to meet the customer’s needs?

  1. A. Rack Management Controller for nPar management
  2. B. HPE Superdome Flex Grid licenses enabling connectivity between chassis
  3. C. At least Tour HPE Persistent Memory DIMMs per nPar
  4. D. One base chassis and three expansion chassis with licenses

Correct Answer: D

QUESTION 8

Your customer plans to deploy VMware ESXi 7 0 U2 and they are looking for a hardware platform mat wilt allow them to use up to 24 TB of physical memory.
Which HPE compute system meets this customer's requirements?

  1. A. HPE ProLiant DL380 Gen 10 Plus
  2. B. HPE Synergy 480 Gen10 Plus
  3. C. HPE ProLiant DL560 Gen10
  4. D. HPE Superdome Flex 280

Correct Answer: A

QUESTION 9

Match each HPE OneView network type with its definition.
HPE0-S59 dumps exhibit
Solution:
HPE0-S59 dumps exhibit

Does this meet the goal?

  1. A. Yes
  2. B. No

Correct Answer: A

QUESTION 10

Your customer wants to add a second HPE Synergy frame to an existing logical enclosure Based on a single HPE Synergy frame. The customer wants to use a highly available master setup.
Which procedures should De performed during the expansion process? (Select two.)

  1. A. Create a new logical interconnect group and enclosure group for two frames setup
  2. B. Create a new logical enclosure based on both HPE Synergy frames.
  3. C. Re-parent an existing enclosure group to the new logical interconnect group.
  4. D. Modify an existing logical interconnect to include second HPE Synergy frame.
  5. E. Move one of the master modules to the appropriate interconnect bay in the second frame.

Correct Answer: BD