QUESTION 36

A four-node Isilon cluster is being used in a Hadoop workflow with a parity protection of N+2:1. The HDFS protocol has been enabled and is being used to access data.
How many additional copies of data are written into the Isilon cluster using HDFS?

  1. A. None
  2. B. One
  3. C. Three
  4. D. Two

Correct Answer: A

QUESTION 37

A potential customer uses a solution from an EMC competitor for NFS storage in their main data center. The existing arrays are five years old, and the customer would like to consolidate them into a single new system. The entire workload is generated by eight Linux hosts connected to the arrays that process video files. The customer informs you they are not able to collect performance information from the existing arrays.
Which tools can capture the workload requirements?

  1. A. iostat and nfsstat
  2. B. MiTrends and netmon
  3. C. netstat and esxtop
  4. D. Wireshark and sysstat

Correct Answer: A

QUESTION 38

An Isilon customer expressed an interest in more effectively managing their storage. Specifically, they would like to plan for future growth.
Which tool would allow the customer to forecast capacity requirements?

  1. A. InsightIQ
  2. B. Isilon SNMP MIB
  3. C. SyncIQ
  4. D. SmartPools

Correct Answer: A

QUESTION 39

An Isilon customer experienced a node failure. The failure requires that the affected node be permanently removed from the cluster. What will occur in the cluster upon failure of the node?

  1. A. OneFS will assume it is a temporary failure and the data will not be protected at the appropriate levels.
  2. B. Cluster will detect the node failure and automatically begin the SmartFail process.
  3. C. FlexProtect will be activated and data will be protected at the appropriate levels.
  4. D. Nothin
  5. E. When data protection levels are set appropriately, OneFS will always protect data without manual interaction.

Correct Answer: A

QUESTION 40

An Isilon customer has two 5-node clusters; one for production and one for disaster recovery (DR). The customer's workflows are replicated to the DR cluster through SyncIQ on individual schedules. They have shut down their production cluster for scheduled maintenance, failed over to the DR cluster, and are currently operating from the DR site.
Assume both clusters have identical shares, exports, user authentication. In addition, assume the client applications have been stopped and the DNS re-pointed. What is the easiest SyncIQ Policy method to continue operations on production?

  1. A. Initiate Automated Failback
  2. B. Revert
  3. C. Initiate Manual Failback
  4. D. No change is needed

Correct Answer: A