QUESTION 76

Which of the following is correct? Debugging is:

  1. A. Testing/checking whether the software performs correctly.
  2. B. Checking that a previously reported defect has been corrected.
  3. C. Identifying the cause of a defect, repairing the code and checking the fix is correct.
  4. D. Checking that no unintended consequences have occurred as a result of a fix.

Correct Answer: C
A. Is a brief definition of testing.
B. Is retesting.
D. Is regression testing.

QUESTION 77

Which of the following test design techniques is classified as a structure-based (white box) technique? [K1]

  1. A. Exploratory testing
  2. B. Decision table testing
  3. C. State transition testing
  4. D. Statement testing

Correct Answer: D

QUESTION 78

You have investigated different possibilities and selected four of them to present to IT management. Which of the proposals will you most likely give your highest recommendations? 3 credits

  1. A. Insourcing of test automation based on an offer from a local company ABC that has people who are specialists in system level capture-replay automation tools and they also do regular training courses in test automation methods and tool
  2. B. They can then work closely with Vicki.
  3. C. Outsourcing of test automation based on an offer from an Asian company, AsiaAutoTest, which has people who are specialists in system level capture-replay automation tool
  4. D. They also offer training and besides they offer to run and maintain the regression tests in the future.
  5. E. Internal offer from the development department of XYZ to create the regression package using CppUnit as test automation too
  6. F. One of the development groups have very good experiences in automating unit tests, and they are willing to do training as well.
  7. G. Solution from a tool vendor offering to educate two test team members in the use of their easy-to-use test automation capture replay tool over the first 3 month and based on that build the regression test suit
  8. H. In addition to Vicki, Steve is the only one that has time available to be educated.

Correct Answer: A

QUESTION 79

Which of the following is a role of a formal review? [K1]

  1. A. Adjudicator
  2. B. Moderator
  3. C. Governor
  4. D. Corrector

Correct Answer: B

QUESTION 80

What if the project isn't big enough to justify extensive testing..?

  1. A. Use automation tool for testing
  2. B. Use risk based analysis to find out which areas need to be tested
  3. C. Both a and b
  4. D. None of the above

Correct Answer: B