QUESTION 21

- (Topic 1)
SCENARIO A Six Sigma team is measuring the moisture content of corn starch as it leaves the conveyer belt of a dryer. They collect one sample four cups of starch at times indicated in the chart at fixed locations labeled A, B, C, and D across the end of the belt. See the diagram below.
CSSBB dumps exhibit
Find the equation of the regression line for these sample data points: (1, 7) (3, 3) ( 3, 2) (5, –1)
CSSBB dumps exhibit

  1. A. y = 10.8 – 2.9x
  2. B. y = 12.9 + 5.2x
  3. C. y = 16 – 3.7x
  4. D. y = 8.75 – 2x
  5. E. y = 22.6 – 4.8x

Correct Answer: D

QUESTION 22

- (Topic 1)
A pharmaceutical manufacturer is designing an experiment to test four different capsule ingredients designed to reduce dissolution time. Each ingredient will be tested at 10 milligrams and 40 milligrams. A full factorial design is used with five replications per run. The number of levels, factors and runs is, respectively:

  1. A. 2, 4, 16
  2. B. 4, 5, 8
  3. C. 10, 4, 40
  4. D. 2, 20, 16

Correct Answer: A

QUESTION 23

- (Topic 2)
A team has been asked to reduce the occurrence of a particular defect. They begin by brainstorming all possible causes using a:

  1. A. matrix diagram
  2. B. cause and effect diagram
  3. C. process decision program chart
  4. D. affinity diagram
  5. E. activity network diagram
  6. F. tree diagram
  7. G. prioritization matrix
  8. H. matrix diagram
  9. I. interrelationship digraph

Correct Answer: B

QUESTION 24

- (Topic 2)
Work performed by the payroll department is considered value added activity.

  1. A. true
  2. B. false

Correct Answer: B

QUESTION 25

- (Topic 2)
A team wants to make a schedule for a project showing which tasks must be done sequentially and which may be done simultaneously. Which tool is most appropriate?

  1. A. matrix diagram
  2. B. cause and effect diagram
  3. C. process decision program chart
  4. D. affinity diagram
  5. E. activity network diagram
  6. F. tree diagram
  7. G. prioritization matrix
  8. H. matrix diagram
  9. I. interrelationship digraph

Correct Answer: E

Page 6 of 60