QUESTION 31

- (Topic 3)
The question below is based on the following illustration of product parts:
CPIM-BSP dumps exhibit
Which of the following items are components?

  1. A. Y and Z only
  2. B. 1, 2, and 3 only
  3. C. Y, Z, 1, 2, and 3 only
  4. D. X, Y, Z, 1, 2, and 3

Correct Answer: C

QUESTION 32

- (Topic 3)
A work center has 2 machines that are operated 16 hours a day for 5 days a week. Historically, the utilization has been 85% and the efficiency 105%. What is the rated capacity for this work center? (Rounded)

  1. A. 71
  2. B. 99
  3. C. 130
  4. D. 143

Correct Answer: D

QUESTION 33

- (Topic 1)
Which of the following situations is characteristic of a make-to-stock environment?

  1. A. Work in process (WIP) represents the largest cost of inventory.
  2. B. The impact of technology on the production process will be large.
  3. C. The master schedule is stated at the finished product level.
  4. D. Customer involvement is typically very high.

Correct Answer: C

QUESTION 34

- (Topic 4)
Which of the following factors would reduce inventory carrying costs?

  1. A. Ordering less inventory
  2. B. Higher costs of working capital
  3. C. Reducing ordering costs
  4. D. Reducing transportation costs

Correct Answer: A

QUESTION 35

- (Topic 4)
Which of the following activities positions goods or services closer to the customer?

  1. A. Distribution
  2. B. Manufacturing
  3. C. Materials handling
  4. D. Transportation

Correct Answer: A