QUESTION 36

- (Topic 1)
Nancy has asked you to trace a particular requirement for her. What does 'to trace a requirement' mean? A. Tracing a requirement means to look at a requirement and the others to which it is related. It links risk, cost, quality, and scope elements to stakeholder and solution requirements to other artifacts created by the team and to solution components.

  1. A. Tracing a requirement means to look at a requirement and the others to which it is relate
  2. B. It links business requirements to stakeholder and solution requirements to other artifacts created by the team and to solution component
  3. C. Tracing a requirement means to look at a requirement and the others to which it is relate
  4. D. It links business requirements to components in the project's work breakdown structur
  5. E. Tracing a requirement means to track a requirements from its first identification all the way to its completion to see what issues, risks, costs, quality, and defects have surrounded the requirement

Correct Answer: B

QUESTION 37

- (Topic 3)
Which of the following is the comparison of planned project results with actual project results?

  1. A. Variance analysis
  2. B. Cost-benefit analysis
  3. C. Statistical Sampling
  4. D. Trend analysis

Correct Answer: A

QUESTION 38

- (Topic 3)
Which of the following terms is used to describe a major deliverable or key even in the project used to measure project progress?

  1. A. Project life cycle
  2. B. Phase
  3. C. Achievement
  4. D. Milestone

Correct Answer: D

QUESTION 39

- (Topic 2)
What type of interview is the most common as part of requirements elicitation?

  1. A. Many-to-one
  2. B. Many-to-many
  3. C. One-to-one
  4. D. One-to-many

Correct Answer: C

QUESTION 40

- (Topic 3)
Which of the following roles approves the project scope statement, phase gate reviews, solution validations, scope changes, and project success criteria?

  1. A. Project manager
  2. B. Subject matter expert
  3. C. Solution owner
  4. D. Stakeholder

Correct Answer: C