- (Topic 2)
You are the business analyst for a solution that has 435 stakeholders. How many communication channels exist in this project?
Correct Answer:
C
- (Topic 2)
You are the business analyst for your organization and are preparing for the conduct elicitationactivity. You'll need several stakeholders' roles as you prepare for this activity in your organization. Which one of the following stakeholders may be responsible to dictate that a specific process or technique be followed during your requirements elicitation activities?
Correct Answer:
B
- (Topic 1)
You are the business analyst for your organization. Management has asked that you create a method to store the project requirements including those under development, under review, and the requirements which have been approved. What is management asking you to create?
Correct Answer:
B
- (Topic 3)
Which of the following compares two or more systems, states, services, products, or things to
determine the best viable choice?
Correct Answer:
A
- (Topic 2)
Management comes to you and asks you to complete some specifications and models
about the current state of the organization. Management wants you to complete this
business analysis activity as soon as possible and report back to them with your findings.
What is the primary purpose of the specify and model requirements process?
Correct Answer:
D