QUESTION 36

- (Exam Topic 5)
When cost variance is negative and schedule variance is positive, the project is:

  1. A. under budget and behind schedule.
  2. B. over budget and ahead of schedule.
  3. C. on schedule.
  4. D. complete; all planned values have been earned.

Correct Answer: B

QUESTION 37

- (Exam Topic 1)
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

  1. A. Bottom-up
  2. B. Parametric
  3. C. Analogous
  4. D. Three-point

Correct Answer: C

QUESTION 38

- (Exam Topic 4)
Managing procurement relationships and monitoring contract performance are part of which process?

  1. A. Conduct Procurements
  2. B. Plan Procurements
  3. C. Administer Procurements
  4. D. Close Procurements

Correct Answer: C

QUESTION 39

- (Exam Topic 4)
An input to the Perform Quantitative Risk Analysis process is the:

  1. A. quality management plan.
  2. B. project management plan.
  3. C. communications management plan.
  4. D. schedule management plan.

Correct Answer: D

QUESTION 40

- (Exam Topic 4)
Which provides the basic framework for managing a project?

  1. A. Project life cycle
  2. B. Work breakdown structure (WBS)
  3. C. Enterprise environmental factors
  4. D. Project initiation

Correct Answer: A