QUESTION 16

- (Exam Topic 2)
An issue log is an input to which Project Human Resource Management process?

  1. A. Manage Project Team
  2. B. Acquire Project Team
  3. C. Plan Human Resource Management
  4. D. Develop Project Team

Correct Answer: A

QUESTION 17

- (Exam Topic 1)
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

  1. A. Stakeholder register
  2. B. Scope management plan
  3. C. Stakeholder management plan
  4. D. Project charter

Correct Answer: A

QUESTION 18

- (Exam Topic 4)
Which process determines the risks that might affect the project?

  1. A. Perform Qualitative Risk Analysis
  2. B. Identify Risks
  3. C. Plan Risk Management
  4. D. Perform Quantitative Risk Analysis

Correct Answer: B

QUESTION 19

- (Exam Topic 1)
Which document describes the necessary information to determine if a project is worth the required investment?

  1. A. Cost baseline
  2. B. Service level agreement
  3. C. Memorandum of understanding
  4. D. Business case

Correct Answer: D

QUESTION 20

- (Exam Topic 3)
The Verify Scope process is primarily concerned with:

  1. A. formalizing acceptance of the completed project deliverables.
  2. B. accuracy of the work deliverables.
  3. C. formalizing approval of the scope statement.
  4. D. accuracy of the work breakdown structure (WBS).

Correct Answer: A