QUESTION 156

- (Exam Topic 1)
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

  1. A. Expert judgment.
  2. B. Analytical techniques.
  3. C. Earned value management.
  4. D. Group decision-making techniques.

Correct Answer: B

QUESTION 157

- (Exam Topic 5)
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

  1. A. operate separately.
  2. B. move together in batches,
  3. C. overlap and interact.
  4. D. move in a sequence.

Correct Answer: C

QUESTION 158

- (Exam Topic 6)
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

  1. A. Organizational process assets
  2. B. Change management plan
  3. C. Communications management plan
  4. D. Resource management plan

Correct Answer: C

QUESTION 159

- (Exam Topic 2)
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

  1. A. Collect Requirements
  2. B. Plan Scope Management
  3. C. Define Scope
  4. D. Define Activities

Correct Answer: A

QUESTION 160

- (Exam Topic 2)
Progressively elaborating high-level information into detailed plans is performed by the:

  1. A. project management office
  2. B. portfolio manager
  3. C. program manager
  4. D. project manager

Correct Answer: D