QUESTION 151

- (Exam Topic 4)
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?

  1. A. Control chart
  2. B. Flowchart
  3. C. Run chart
  4. D. Pareto chart

Correct Answer: B

QUESTION 152

- (Exam Topic 6)
The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?

  1. A. Work performance information
  2. B. Bidder conferences
  3. C. Complexity of procurement
  4. D. Procurement management plan

Correct Answer: D

QUESTION 153

- (Exam Topic 2)
Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

  1. A. Estimate Costs
  2. B. Control Costs
  3. C. Plan Cost Management
  4. D. Determine Budget

Correct Answer: D

QUESTION 154

- (Exam Topic 6)
When managing costs in an agile environment, what should a project manager consider?

  1. A. Lightweight estimation methods can be used as changes arise.
  2. B. Agile environments make cost aggregation more difficult.
  3. C. Agile environments make projects more costly and uncertain.
  4. D. Detailed cost calculations benefit from frequent changes.

Correct Answer: A

QUESTION 155

- (Exam Topic 5)
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

  1. A. Manage Stakeholder Expectations.
  2. B. Monitor and Control Risks.
  3. C. Plan Risk Management.
  4. D. Report Performance.

Correct Answer: A