- (Exam Topic 5)
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
Correct Answer:
C
- (Exam Topic 1)
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
Correct Answer:
C
- (Exam Topic 1)
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
Correct Answer:
C
- (Exam Topic 6)
Which tasks should a project manager perform in order to manage the project schedule effectively?
Correct Answer:
B
- (Exam Topic 2)
A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?
Correct Answer:
D