- (Exam Topic 3)
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
Correct Answer:
D
- (Exam Topic 6) Given the following information. Activity A takes one week.
Activity B takes three weeks. Activity C takes two weeks. Activity D takes five weeks.
Activity A starts at the same time as Activity B. Activity C follows Activity B and Activity A. Activity D follows Activity C.
How long will it take to complete the project?
Correct Answer:
D
- (Exam Topic 6)
What are the objectives of Initiation processes?
Correct Answer:
D
- (Exam Topic 4)
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
Correct Answer:
C
- (Exam Topic 6)
The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?
Correct Answer:
C