QUESTION 6

- (Exam Topic 3)
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?

  1. A. Scope plan
  2. B. Product scope
  3. C. Scope management plan
  4. D. Scope baseline

Correct Answer: D

QUESTION 7

- (Exam Topic 6) Given the following information. Activity A takes one week.
Activity B takes three weeks. Activity C takes two weeks. Activity D takes five weeks.
Activity A starts at the same time as Activity B. Activity C follows Activity B and Activity A. Activity D follows Activity C.
How long will it take to complete the project?

  1. A. Eleven weeks
  2. B. Nine weeks
  3. C. Eight weeks
  4. D. Ten weeks

Correct Answer: D

QUESTION 8

- (Exam Topic 6)
What are the objectives of Initiation processes?

  1. A. Initiation processes are performed in order to develop the project charier and Identify stakeholders.
  2. B. Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.
  3. C. Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders' goals.
  4. D. Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.

Correct Answer: D

QUESTION 9

- (Exam Topic 4)
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

  1. A. Cost-reimbursable contracts
  2. B. Time and Material contracts (T&M)
  3. C. Fixed-price contracts
  4. D. Cost Plus Fixed Fee Contracts (CPFF)

Correct Answer: C

QUESTION 10

- (Exam Topic 6)
The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?

  1. A. Technical project management skills
  2. B. Time management skills
  3. C. Strategic and business management skills
  4. D. Leadership skills

Correct Answer: C