QUESTION 131

- (Exam Topic 4)
Which of the following is an example of the simplest fixed-price contract?

  1. A. Purchase requisition
  2. B. Purchase order
  3. C. Verbal agreement
  4. D. Request for quote

Correct Answer: B

QUESTION 132

- (Exam Topic 3)
The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

  1. A. Push
  2. B. Pull
  3. C. Interactive
  4. D. Iterative

Correct Answer: B

QUESTION 133

- (Exam Topic 2)
Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

  1. A. Business case
  2. B. Work breakdown structure
  3. C. Requirements documentation
  4. D. Risk register

Correct Answer: C

QUESTION 134

- (Exam Topic 5)
A project lifecycle is defined as:

  1. A. a collection of generally sequential and sometimes overlapping project phases.
  2. B. a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
  3. C. a recognized standard for the project management profession.
  4. D. the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Correct Answer: A

QUESTION 135

- (Exam Topic 6)
Match the influence with its corresponding category of influence.
CAPM dumps exhibit
Solution:
CAPM dumps exhibit

Does this meet the goal?

  1. A. Yes
  2. B. No

Correct Answer: A