Free CAPM Exam Braindumps

Pass your Certified Associate in Project Management (PMI-100) exam with these free Questions and Answers

Page 26 of 180
QUESTION 121

- (Exam Topic 6)
It you established a contingency reserve including time, money, and resources, how are you handling risk?

  1. A. Accepting
  2. B. Transferring
  3. C. Avoiding
  4. D. Mitigating

Correct Answer: A

QUESTION 122

- (Exam Topic 6)
What purpose does the hierarchical locus of stakeholder communications serve?

  1. A. Maintains the focus on project and organizational stakeholders
  2. B. Preserves the tocus on external stakeholders—such as customers and vendors—as well as on other projects
  3. C. Sustains the focus on general communication activities using email, social media, and websites
  4. D. Keeps the focus on the position of the stakeholder or group with respect to the project team

Correct Answer: C

QUESTION 123

- (Exam Topic 6)
What can increase the complexity of the Manage Stakeholder Engagement process?

  1. A. The project must be of high quality.
  2. B. The stakeholders are from different countries.
  3. C. The project must comply with strict local government regulations.
  4. D. The project has a tight budget and timeline.

Correct Answer: B

QUESTION 124

- (Exam Topic 6)
Which two processes should be used to influence costs in the early stages of a project?

  1. A. Estimate Costs and Determine Budget
  2. B. Plan Cost Management and Estimate Activity Durations
  3. C. Control Quality and Control Costs
  4. D. Plan Stakeholder Engagement and Plan Communications Management

Correct Answer: A

QUESTION 125

- (Exam Topic 5)
The correct equation for schedule variance (SV) is earned value:

  1. A. minus planned value [EV - PV].
  2. B. minus actual cost [EV - AC].
  3. C. divided by planned value [EV/PV],
  4. D. divided by actual cost [EV/AC].

Correct Answer: A

Page 26 of 180

Post your Comments and Discuss PMI CAPM exam with other Community members: