QUESTION 111

- (Exam Topic 1)
Which tool or technique is used to develop the human resource management plan?

  1. A. Ground rules
  2. B. Expert judgment
  3. C. Team-building activities
  4. D. Interpersonal skills

Correct Answer: B

QUESTION 112

- (Exam Topic 2)
The following chart contains information about the tasks in a project.
CAPM dumps exhibit
Based on the chart, what is the schedulevariance (SV) for Task 8?

  1. A. A.--2,000B.-1,000C.1,000D.2,000

Correct Answer: B

QUESTION 113

- (Exam Topic 1)
A key benefit of the Manage Communications process is that it enables:

  1. A. The best use of communication methods.
  2. B. An efficient and effective communication flow.
  3. C. Project costs to be reduced.
  4. D. The best use of communication technology.

Correct Answer: B

QUESTION 114

- (Exam Topic 6)
A project stakeholder is requesting changes to the project plan. Which process group addresses this?

  1. A. Initiating Process Group
  2. B. Planning Process Group
  3. C. Executing Process Group
  4. D. Monitoring and Controlling Process Group

Correct Answer: D

QUESTION 115

- (Exam Topic 5)
An input to the Estimate Activity Resources process is:

  1. A. Activity resource requirements.
  2. B. Published estimating data.
  3. C. Resource calendars.
  4. D. Resource breakdown structure (RBS).

Correct Answer: C