Free CAPM Exam Braindumps

Pass your Certified Associate in Project Management (PMI-100) exam with these free Questions and Answers

Page 2 of 180
QUESTION 1

- (Exam Topic 2)
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

  1. A. adaptive
  2. B. reflexive
  3. C. predictive
  4. D. iterative

Correct Answer: A

QUESTION 2

- (Exam Topic 3)
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

  1. A. Define Activities.
  2. B. Sequence Activities.
  3. C. Define Scope.
  4. D. Control Schedule.

Correct Answer: A

QUESTION 3

- (Exam Topic 6)
A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

  1. A. What-if scenario analysis
  2. B. Simulation
  3. C. Alternatives analysis
  4. D. Reserve analysis

Correct Answer: D

QUESTION 4

- (Exam Topic 1)
An output of the Plan Quality Management process is:

  1. A. A process improvement plan,
  2. B. Quality control measurements.
  3. C. Work performance information,
  4. D. The project management plan.

Correct Answer: A

QUESTION 5

- (Exam Topic 3)
Which is one of the major outputs of Sequence Activities?

  1. A. Responsibility assignment matrix (RAM)
  2. B. Work breakdown structure (WBS) update
  3. C. Project schedule network diagram
  4. D. Mandatory dependencies list

Correct Answer: C