QUESTION 76

- (Exam Topic 1)
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

  1. A. Expert judgment
  2. B. Forecasting methods
  3. C. Earned value management
  4. D. Analytical techniques

Correct Answer: D

QUESTION 77

- (Exam Topic 6)
The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?

  1. A. Plan Resource Management
  2. B. Estimate Activity Resources
  3. C. Estimate Costs
  4. D. Acquire Resources

Correct Answer: B

QUESTION 78

- (Exam Topic 1)
What are the Project Procurement Management processes?

  1. A. Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
  2. B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
  3. C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
  4. D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Correct Answer: C

QUESTION 79

- (Exam Topic 5)
The staffing management plan is part of the:

  1. A. organizational process assets.
  2. B. resource calendar.
  3. C. human resource plan.
  4. D. Develop Project Team process.

Correct Answer: C

QUESTION 80

- (Exam Topic 5)
Risk exists the moment that a project is:

  1. A. planned.
  2. B. conceived.
  3. C. chartered.
  4. D. executed.

Correct Answer: B