QUESTION 71

- (Exam Topic 2)
Variance and trend analysis is a tool and technique used in which process?

  1. A. Perform Qualitative Risk Analysis
  2. B. Perform Quantitative Risk Analysis
  3. C. Control Risks
  4. D. Plan Risk Responses

Correct Answer: C

QUESTION 72

- (Exam Topic 4)
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

  1. A. Executing.
  2. B. Initiating,
  3. C. Monitoring and Controlling.
  4. D. Planning.

Correct Answer: C

QUESTION 73

- (Exam Topic 3)
Which illustrates the connection between work that needs to be done and its project team members?

  1. A. Work breakdown structure (WBS)
  2. B. Network diagrams
  3. C. Staffing management plan
  4. D. Responsibility assignment matrix (RAM)

Correct Answer: D

QUESTION 74

- (Exam Topic 6)
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

  1. A. create the project management plan.
  2. B. identify the project objectives.
  3. C. review and update stakeholder engagement.
  4. D. create the schedule baseline.

Correct Answer: C

QUESTION 75

- (Exam Topic 3)
Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

  1. A. Develop Project Management Plan
  2. B. Develop Project Charter
  3. C. Direct and Manage Project Execution
  4. D. Collect Requirements

Correct Answer: B