- (Exam Topic 3)
The procurement process that documents agreements and related documentation for future reference is known as:
Correct Answer:
C
- (Exam Topic 1)
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
Correct Answer:
B
- (Exam Topic 4)
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
Correct Answer:
D
- (Exam Topic 5)
Which of the following is an input to the Develop Project Charter process?
Correct Answer:
C
- (Exam Topic 5)
Which of the following is an estimating technique that uses the values of parameters from previous similar
projects for estimating the same parameter or measure for a current project?
Correct Answer:
D