QUESTION 61

- (Exam Topic 3)
The procurement process that documents agreements and related documentation for future reference is known as:

  1. A. Plan Procurements.
  2. B. Control Procurements.
  3. C. Close Procurements.
  4. D. Conduct Procurements.

Correct Answer: C

QUESTION 62

- (Exam Topic 1)
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

  1. A. Project management plan.
  2. B. Project charter.
  3. C. Work breakdown structure.
  4. D. Stakeholder register.

Correct Answer: B

QUESTION 63

- (Exam Topic 4)
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

  1. A. US$S000
  2. B. US$9500
  3. C. US$10,000
  4. D. US$12,500

Correct Answer: D

QUESTION 64

- (Exam Topic 5)
Which of the following is an input to the Develop Project Charter process?

  1. A. Work performance information
  2. B. Project management plan
  3. C. Business case
  4. D. Change requests

Correct Answer: C

QUESTION 65

- (Exam Topic 5)
Which of the following is an estimating technique that uses the values of parameters from previous similar
projects for estimating the same parameter or measure for a current project?

  1. A. Reserve analysis
  2. B. Three-point estimating
  3. C. Parametric estimating
  4. D. Analogous estimating

Correct Answer: D

Page 14 of 180