QUESTION 41

- (Exam Topic 2)
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

  1. A. risk management plan
  2. B. human resource management plan
  3. C. scope management plan
  4. D. procurement management plan

Correct Answer: D

QUESTION 42

- (Exam Topic 1)
A large portion of a projects budget is typically expended on the processes in which Process Group?

  1. A. Executing
  2. B. Planning
  3. C. Monitoring and Controlling
  4. D. Closing

Correct Answer: B

QUESTION 43

- (Exam Topic 6)
What scenario describes when a project must be created due to market demand?

  1. A. A public company authorizes a project to create a new service for electric car sharing to reduce pollution.
  2. B. A car company authorizes a project to build more fuel-efficient cars in response to gasoline shortages.
  3. C. Researchers develop an autonomous ca
  4. D. with several new features to be commercialized in the future.
  5. E. Stakeholders request that raw matenais be changed due to locally high costs.

Correct Answer: B

QUESTION 44

- (Exam Topic 1)
Which document defines how a project is executed, monitored and controlled, and closed?

  1. A. Strategic plan
  2. B. Project charter
  3. C. Project management plan
  4. D. Service level agreement

Correct Answer: C

QUESTION 45

- (Exam Topic 2)
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

  1. A. work package
  2. B. deliverable
  3. C. milestone
  4. D. activity

Correct Answer: A