QUESTION 16

A team decided to install a large traffic light in the team hall to indicate whether the latest build was healthy (green), failing a few tests (orange) or failing high priority tests (red).
What term can be used to describe the traffic light?

  1. A. Information radiator
  2. B. Osmotic communication
  3. C. Triangulation

Correct Answer: A

QUESTION 17

What is the expected outcome of the first Sprint on a project?

  1. A. A few working, tested features from the Product Backlog
  2. B. Architecture and high-level design of the Product
  3. C. Assignment of the team, Product Owner and Scrum Master
  4. D. A well-defined release plan for the Product

Correct Answer: A