QUESTION 6

Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?

  1. A. If more details are needed during Sprint Planning
  2. B. If there is a large number of stories to estimate
  3. C. If there is a small number of stories to estimate

Correct Answer: B

QUESTION 7

Sprint planning should result in a commitment on what will be delivered at the end of the Sprint. Who makes this commitment?

  1. A. The Product Owner
  2. B. The Scrum Master
  3. C. The team

Correct Answer: C

QUESTION 8

Who is responsible for implementing the actions agreed upon by the team during a Retrospective?

  1. A. The Product Owner
  2. B. The Scrum Master
  3. C. The team

Correct Answer: C

QUESTION 9

Who knows most about the progress towards a business objective or a release?

  1. A. The Product Owner
  2. B. The Scrum Master
  3. C. The team

Correct Answer: A

QUESTION 10

A team has eleven members spread over two locations across two time zones. One of the locations has six team members and the other team has five.
Where should a Scrum Master be located?

  1. A. Alternate the Scrum Master between both locations.
  2. B. Appoint a local Scrum Master for both teams.
  3. C. The Scrum Master is located in one of the teams.

Correct Answer: B