QUESTION 1

During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13.
What is the velocity of the team?

  1. A. 18
  2. B. 24.5
  3. C. 31

Correct Answer: A

QUESTION 2

Which means of communication is the most preferable to clarify the interpretation of a requirement?

  1. A. E-mail
  2. B. Face-to-face
  3. C. Instant messaging
  4. D. Telephone

Correct Answer: B

QUESTION 3

A Project Manager wants to track not just the rate of progress against tasks, but also the overall morale and happiness of the Scrum team.
What device will help track morale and happiness?

  1. A. A Gross Happiness index
  2. B. A Niko-niko calendar
  3. C. An employee satisfaction survey

Correct Answer: B

QUESTION 4

What should the Scrum Master advise the team to give their main focus, while working in a global distributed team?

  1. A. Favor conference calls and video chats in order to save on travel budget.
  2. B. Place greater emphasis on team-building activities and cultural sensitivities.
  3. C. Provide at least four hours of overlap time by changing working hours.

Correct Answer: B

QUESTION 5

What is a Sprint?

  1. A. A brainstorming session in Extreme programming to generate design ideas.
  2. B. A race between two developers to see who can complete a feature fastest.
  3. C. One iteration in the Scrum methodology.
  4. D. The last iteration in the Scrum project, when the team works long hours to finish the project.

Correct Answer: C